Game Design, Programming and running a one-man games business…

Solar farm mini-update: Waiting for rego

I haven’t mentioned my solar farm for a bit, because frankly nothing has happened. This is extremely frustrating, to put it mildly. Anyway, we have been beset by the evils of bureaucracy and delays again. The REGO stuff is taking ages, and we have been waiting on agreement on earthing…

Solar farms need earthing, in case of lightning strikes etc, and earthing 3,024 solar panels, inverters and a lot of metal framework is a big task. Because the soil at each site is different, the amount of earthing you need differs, and also the topography of each site differs, its not a standard thing that applies everywhere. We have CCTV masts, a surrounding fence (which will be mostly wooden posts IIRC, but definitely has metal components), a metal gate, a substation, and switchgear. The earthing for all of this has to be designed so its safe.

What causes mayhem is that the earthing has to be approved by the DNO (who will have their own substation), but they only design ‘their bit’ and then we have to use external consultants to design our bit, and then both sides have to agree that the other sides design doesn’t interfere with them, and then you can proceed. This involves at least 5 companies (mine, the HV consultant, the farm developer, the DNO and the earthing specialist), and everyone seems to take it in turns to have summer holidays, which has stretched things out enormously :(

The trouble is you cant do digging for foundations for the substation until you know what earthing grid you need. Without the earthworks you cant have the substation, without the substation you cant move the HV line. Without moving the HV line, we cant finish the panels…

So anyway, we finally have agreement (I think) on what the earthing design is, which means we can now start implementing it, which means we can do the substation foundations, and then the actual substation and switchgear install, and also then the meter install, the final panels & frames, and the moving of the HV line. We also need to do CCTV and perimeter fencing…and then its done!

At the same time (because I like to keep SOME progress happening) I have been trying to get certified for REGOs, to prove I am a renewable generator, and thus earn a higher rate for selling my power. This involves a hugely confusing process to fill out a form on a website from 1970, whereupon your application just sits in a pile and is totally ignored. Welcome to the UK government, and its 0.001% level of efficiency. Quite why there is a delay of more than 24 hours for a REGO application is beyond me, but I strongly suspect its something that I can do nothing about, that no politician will ever fix, and that just acts as yet another irritating drag on productivity because this is seemingly a country in terminal decline :(.

I have already chased my application by email twice, but obviously they get ignored too. I’m away for a week, and planning on starting with daily phone calls to chase it once I get back. I make no excuse for being annoying with stuff like this. If the system was well managed nobody would ever have to chase anything, but here we are…

Anyway, thats the update. No pictures to show, nothing to report except waiting, and waiting and waiting :(. The latest guess I have for energisation is early November, which frankly I would be content with.

Its gloriously sunny here today.